Challenge

The bank's 3-Tier architecture (Storage/SAN/Servers) running VMware was expensive to maintain and complex to manage. With Broadcom's acquisition of VMware driving licensing costs up significantly, the bank needed a cost-effective alternative that would simplify operations without compromising reliability.

Approach

Planned and executed a phased migration to hyperconverged infrastructure:

  • Audited existing VMware vSphere environment and workload requirements
  • Designed Nutanix AHV cluster architecture with proper sizing
  • Developed migration plan with risk assessment and downtime windows
  • Migrated virtual machines in phases, starting with non-critical workloads
  • Configured PostgreSQL HA clusters on the new platform
  • Trained internal team on Nutanix Prism management

Results

  • Reduced operational costs through elimination of separate storage and SAN infrastructure
  • Simplified infrastructure management with single-pane-of-glass via Nutanix Prism
  • Reduced support team requirements due to simplified architecture
  • Improved performance with NVMe-based hyperconverged storage